|
Degremont / Thiess / Nacap
Victorian Desalination Plant Project - Installation of Sheetpiling
Victorian Desalination Project Pipeline - Access & Receival pits. Works to include the supply & installation of 1188 no. 600mm wide, 12m, 16m & 19m long Sheet piles at 9 separate locations, excavation of jacking & receival pits, structural steel and concrete works, and all backfilling operations.
Location: South Gippsland, VIC
Expected Completion: April 2011
|
 |
|
Hamersley Iron-Yandi Pty Ltd (Rio
Tinto)
Yandicoogina New Access Road & Related Civil Works
Bulk earthworks and construction for a new 2.2km access road at Rio Tinto’s Yandicoogina Mine Site. Works to include all filling, compaction, paving & drainage requirements including the installation of approximately 12 drainage culverts.
Location: Yandicoogina, WA
Expected Completion: June 2010
|
 |
|
Hamersley Iron-Yandi Pty Ltd (Rio
Tinto)
Yandicoogina Levee Bank
Bulk earthworks and construction of 480m of Levee Bank at Rio Tinto's Yandicoogina mine site.
Location: Yandicoogina, WA
Completed: April 2010
|
 |
|
HWE Mining Pty Ltd
Seawall Embankment Construction
Installation of 460m of sheet piles along a seawall on Cockatoo Island off the Western Australian Coastline. Sheets are up to 16m in lengths and of two different profiles.
Location: Cockatoo Island, WA
Expected Completion: July 2010
|
 |
|
Abigroup
Australian Marine Complex (AMC) Service & Supply Base - Piling Works
This project is designed as a barge berth for Chevron’s Gorgon Project. Austral’s scope was to install 409 No. paired sheetpiles to form 295m main wall and 260m anchor wall. Sheetpiles were installed in lengths of up to 19m long using a Banut 655 and leader-guided vibrator. 6 No. mooring piles were also installed with diameters of 762mm and 914mm. Works were completed 1 month ahead of schedule.
Location: Henderson, WA
Completed: February 2010
|
 |
|
Hamersley Iron-Yandi Pty Ltd (Rio
Tinto)
Access Road Tunnel Installation
Installation of Multi Plate Arch Tunnel for New
Mine Access Road and Screening, Placement and compaction of fill around
tunnel to enable Haul trucks to cross over.
Location: Yandicoogina, WA
Completed: January 2010
|
|
|
Thiess
Sino Iron Causeway Creek Crossing Piling Works & Bridge Deck Installation Works
Installation of 159 number, 610 diameter piles and construction of a 120m long x 28m wide bridge structure. Works include the design and fabrication of a falseworks system to enable hand over hand installation of the piles, the welding in place of 23 Number Steel headstocks and the installation of 600 No. precast planks then the pouring of 920m3 of insitu concrete to form the deck.
Location: Cape Preston, WA
Completed: December 2009
|
 |
Fremantle Port Authority
Reconstruction of Berth 10
Project involves the installation of over 450 piles for the reconstruction of Berth 10 and future deepening of the inner harbour. The works include 610mm & 813mm diameter wharf piles and 610mm diameter clutched tubular piles.
Location: Fremantle, WA
Completed: December 2009
|
|
|
Robe River Iron (Rio Tinto)
West Angelas Village Upgrade
Major upgrade of the existing accommodation village infrastructure at West Angelas to provide a consistent standard of accommodation for all equivalent full time employees, improved recreational facilities, reliable services infrastructure and improved functionality.
Location: West Angelas, WA
Completed: August 2009
|
 |
Robe River Iron (Rio Tinto)
Wash Bay
Installation of infrastructure for collecting and cleaning storm water and process water. The infrastructure will treat the water of hydrocarbon and sediment contamination. Once treated the water will be reused at the mine landform area for water storage and reticulation. It will be located in the vicinity of the washdown pad and workshop at the West Angelas mine site.
Location: West Angelas, WA
Completed: August 2009
|
 |
Robe River Iron (Rio Tinto)
Workshop & Office Facility General Installation
Construction of an office facility and an erection of a workshop facility for the maintenance of plant equipment. This includes earthworks, footing and slab construction, installation of hydraulic services, power supply and compressed air piping.
Location: West Angelas, WA
Completed: August 2009
|
 |
Robe River Iron (Rio Tinto)
AN Facility Drainage Upgrade
Perform necessary earthworks for the construction of the upgraded drainage path for the AN facility. Also includes the construction of windrows, an evaporation pond and installation of 240V power point adjacent to the new calibration pad.
Location: West Angeles, WA
Completed: May 2009 |
 |
Pilbara Iron Company Pty Ltd
East Intercourse Island Structural Remedial Works
Hire of Swissco Marine V barge, 250 tonne crane and 3 man crew to perform lifts and modifications to East Intercourse Island Wharf. Minimum of 16 weeks hire.
Location: Dampier, WA
Completed: December 2008 |
 |
Hamersley Iron (Rio Tinto)
MEM Lube Storage Shed
Construction of a MEM Lube Storage Shed. The Shed will be used to store bulk lube containers and will be a loading and unloading point for lube service trucks. The new shed will comply with relevant Rio Tinto and Australian Standards for storage of hydrocarbons.
Location: Paraburdoo, WA
Completed: December 2008
|
 |
Robe River Iron (Rio Tinto)
Wash Bay Stage 1
Installation of infrastructure for collecting and cleaning storm water and process water. The infrastructure will treat the water of hydrocarbon and sediment contamination. Once treated, the water will be re-used at the mine landform area for water storage and reticulation. It will be located in the vicinity of the washdown pad and workshop at the West Angelas mine site.
Location: West Angelas, WA
Completed: December 2008
|
 |
Hamersley Iron (Rio Tinto)
Eastern Ranges Ore Crusher Sediment Pond
Excavation and earthworks carried out for the construction of a sediment pond including PVC liner to embankment, concrete spillway and placement of rip rap.
Location: Paraburdoo, WA
Completed: August 2008
|
 |
Rio Tinto Pty Ltd
Tom Price Contaminated Water Management
Construction and additions to the existing water management systems within the mine to collect and clean contaminated water from the mine. The project involves structural concrete works and earthworks in a working mine site.
Location: Tom Price, WA
Completed: August 2007
|
 |
Construction Engineering
VRC Flemington Race Course Upgrade Project
Construction of a temporary sheetpiled cofferdam in three stages for construction of a cast insitu concrete tunnel to enable the secure movement of racehorses between the new stables and the Birdcage. The full perimeter cofferdam requires 12 metre long L607 profile sheetpiles fully vibrated into saturated coode island silt to privide our client with a semi-dry enclosure to open tunnel whilst progressivley installing waler steelwork and propping beams.
Location: Flemington, Vic
Completed: August 2007
|
 |